Requirements for removal prior to demolition or renovation:

303.3 Scheduling of Demolition Activities: RACM shall be removed prior to demolition, or other operations that would either break up, or preclude access to the RACM for subsequent removal. Removal of RACM which is encased in concrete or other similar structural material is not required prior to demolition, but such material shall be adequately wetted whenever exposed during demolition or renovation and disposed of as RACM as required in Section 304.

 

Requirements for survey prior to demolition or renovation:

303.8 Surveys: Except for ordered demolitions, prior to commencement of any demolition or renovation, the owner or operator shall thoroughly survey the affected structure or portion thereof for the presence of asbestos-containing material, including Category I and Category II nonfriable asbestos-containing material.. The survey shall be performed by a person who is certified by the Division of Occupational Safety and Health, and who has taken and passed an EPA-approved Building Inspector course and who conforms to the procedures outlined in the course. The survey shall include sampling and the results of laboratory analysis of the asbestos content of all suspected asbestos-containing materials. This survey shall be made available, upon request by the APCO, prior to the commencement of any RACM removal or any demolition. This subsection shall not apply if the owner or operator asserts that the material to be renovated is RACM and will be handled in accordance with the provisions of Sections 11-2-303, 304 and 401. The requirement for certification by the Division of Occupational Safety and Health shall not apply to in-house health professionals within a specific non-asbestos related company who perform occasional surveys only for that company as part of their regular job responsibilities.

303.8.1 When a structure, or portion thereof, is demolished under an ordered demolition, the survey must be done prior to, during, or after the demolition but prior to loading or removal of any demolition debris. If the debris contains regulated asbestos-containing material, all of the debris shall be treated as asbestos-containing waste material pursuant to Section 11-2-304.

303.8.2 For renovation or demolition of residential buildings having four or fewer dwelling units, a survey is not required. A sample and test of the material will be required only when any of the following will be removed or disturbed: heating, ventilation, air conditioning ducting and systems; acoustic ceiling material or acoustic plaster; textured or skim coated wall surfaces, cement siding or stucco, or resilient flooring. Where the material if found to contain greater than 1 percent asbestos and is friable, the material must be handled in accordance with Section 11-2-303.